Auckland Transport and their contractor are carrying out road resurfacing work at Easton Park Parade and the Stanley Road/Kaipatiki Rd roundabout this month. This work will repair wear and tear to keep the roads in top shape. Traffic control or diversions will be in place during the roadworks.
Easton Park Parade:
Work will be carried out at night from 20th March-21st March 2019. The contingency date is 24th March 2019.
Stanley Road/Kaipatiki Road Roundabout:
Work will be carried out at night from 24th March-26th March 2019. The contingency date is 27th March 2019.